Hardware Sample Acceptance

Decide what the first sample must prove and record the checks needed before approving a pilot build.

Browse the detailed guide

Example: planning a two-day visit for a connected device

Imagine a hardware team with a working desk-device prototype. It wants to evaluate a smaller display and find out whether a pilot assembly run is realistic. Its brief lists the display interface, enclosure envelope and three functional checks. It also states the tentative pilot quantity and which mechanical details can still change.

On the first day, the team compares two working display samples in Huaqiangbei. It records exact model, connector and driver requirements before asking for sample and pilot prices. The team keeps a record of which sample it demonstrated and which one it purchased. If the two samples use different connectors, it leaves that difference visible instead of treating the price gap as a saving.

For the second day, the team requests an assembly discussion around one specific question: who would run the programming and final functional test? It confirms the production location and process in advance. If line access falls through, it asks for a technical meeting and a sample test record. If the purchase decision requires live evidence, it reschedules the factory visit.

The outcome is a bench-test plan for the displays and one comparable manufacturing request, with missing evidence attached. This is an illustrative project, not a past customer result.

From first sample to approved pilot

  1. Design revision frozen for the sample. Record the exact files, approved equivalents and open changes that do not affect the sample test.
  2. First article checked. Document measurements and functional results using the same method for each sample. Identify whether the build used the same material and process intended for the pilot.
  3. Revisions documented. If a supplier changes material, component or tool, write down why and what must be retested. Approve any substantive change before the next run.
  4. Pilot acceptance agreed. Confirm lot size, first-piece review, unit checks, packing and handling of rejected units. Attach the relevant drawing revision to the written quote.
  5. Reorder path identified. Keep contact, batch, approved revision and cost breakdown with the test record. Ask which purchase terms or lead times will change on a repeat order.